Started too big or thought too small: the five questions for warehouse automation

Warehouse automation does not start with technology but with five questions. What do you want to solve, how does your warehouse work now, what level of automation fits, is it feasible and can you implement it?

Warehouse automation does not start with technology, but with five questions: what do you want to solve, how does your warehouse work now, what level of automation fits, is it feasible on more than ROI alone, and can you implement it without bringing the operation to a standstill. If you cannot answer those five, you are not yet ready for supplier selection.

The two ways it goes wrong

In 2026, those responsible for warehouses have several things to manage at once. Product ranges are growing, costs are under pressure, peaks are getting sharper and staff are scarce at every level. Automation offers a way forward. But it goes wrong in two ways, and both are expensive.

Starting too big. You measure yourself against the top cases in the trade media, choose a solution that suits an organisation three times your size, and pay for years for capacity you do not use.

Thinking too small. You barely know the new technologies, choose the safe step, and are stuck again within two years.

There is a third mistake that is less noticeable and more common: falling in love with technology. An impressive shuttle or AGV solves nothing if the underlying process is shaky. If you automate a messy process, you get a fast and expensive version of that same mess.

Question 1: what do you really want to solve?

Before a supplier comes to the table, the business question has to be sharp. In practice, our engineers see four drivers, usually in combination.

Then answer three questions: which of these four is the most important for us and which is a consequence of the others, what does this problem cost us per week today, and what happens if we do nothing while volume rises?

Question 2: do you know how your warehouse works now?

Without figures you are steering on gut feeling. Map out how work flows through your warehouse today, from inbound via storage, replenishment, picking and packing to outbound. What you want to have in view as a minimum:

This step almost always produces surprises. One company that thought it had a storage problem turned out, once it measured, to be losing time mainly in order picking because of long walking routes. In that case a smarter layout makes more sense than extra racking, and it saves an investment of a different order. Measuring prevents you from investing in a solution to a problem you do not have.

Question 3: what level of automation fits?

Automation is not all or nothing. The first gains are often lower down than people think.

Think in suitable combinations, not in black-and-white choices. Select on peak capacity, scalability, flexibility when the product range changes, investment level, risk in the event of downtime and operational impact on the people on the floor. The right choice depends on your volumes, your growth and your payback period, not on which supplier gave the best demo.

Question 4: is it feasible, beyond ROI?

A payback period on a single sheet of A4 is not yet a feasible plan. Test on four axes, and all four have to add up.

Do not forget the softer benefits. Fewer physically demanding tasks make your warehouse more attractive as an employer, and more reliable deliveries strengthen the relationship with your clients.

Question 5: can you implement it without bringing the operation to a standstill?

A design on paper is not yet a running warehouse. During implementation the logistics flows simply continue. The phasing we use: design, build, test, training, go-live and aftercare.

Two things that go wrong most often. The first is overrun: identify causes in time and budget early and ask the question that gets asked too late, namely whether the people who were promised are really available or still have their daily work alongside it. The second is aftercare: most projects stop at go-live, while that is exactly where optimisation begins.

In practice: HBM Machines

HBM Machines had four separate warehouses in the Benelux. These have been brought together in one central distribution centre, with a new warehouse management system and a substantial package of mechanisation: racking, automated packing, a lift system and conveyor mechanisation. UC Group's logistics engineers guided the project from design until after go-live, including the move while the operation kept running.

The story did not stop at go-live in 2022. During the first Black November, teething problems came to light. In the improvement programme that followed, the alignment between the control layer and the WMS was improved and the way of picking was redefined per product group. Productivity then rose by almost twenty per cent and the November peak was handled better.

The lesson: even a well-designed warehouse is not finished at go-live. Count on a period of fine-tuning and organise it in advance.

What you can do next week

Do not start by calling suppliers. Start by measuring. Pick a week, record the order profiles and the lead times per process step, and look at where the work really gets stuck. That one week of data changes minds more often than six months of demos.

Would you like to go through the five questions for your own warehouse? Our logistics engineers do that in 45 minutes and afterwards you receive brief feedback with three observations. Get in touch.

Frequently asked questions

Where do you start with warehouse automation?

With your process and your data, not with the technology. First map out how your warehouse works now and where the bottlenecks are. Only then do you determine which layout or automation adds value.

Do I need to have my processes in order before I automate?

For the most part, yes. If you automate a messy process, you get a fast and expensive version of that same mess. What you do not have to do is wait until everything is perfect: the low-threshold improvements in layout and WMS logic are often the first step in themselves.

How do I know whether I am starting too big?

If the business case only adds up at volumes you are not yet achieving and do not expect on solid grounds, you are starting too big. So always calculate with scenarios, including the scenario in which growth is disappointing.

When is automation not yet on the agenda?

If you do not have the four drivers sharp, if your order profiles and lead times have not been measured, or if the low-threshold gains in layout and WMS control are still on the table. Those gains are cheaper and often fund the next step.

What do the costs depend on?

On the level of automation, on your volumes and on the extent to which your existing systems connect. A better layout with sharper WMS logic is a different order of magnitude from automated storage. Alongside the investment, also calculate the savings on labour, space, errors and lead time.

Watch the webinar

This article stems from our Warehouse Automation webinar, in which our logistics engineers, together with Kardex, go through orientation, the selection process, feasibility and implementation, with examples from practice.

Watch the full recording of the webinar